Défi de la ville de Moncton
Par Darryl Bonhower, ingénieur
(version anglaise seulement)
Background
The Moncton Downtown Center (MDC) was constructed on the former site of the Highfield Square shopping center adjacent to the CN/VIA Rail station in the heart of Moncton’s downtown. In order to prepare for this redevelopment, downstream sewer systems had to be improved. Additionally, stormwater management in the form of detention storage was required in order to meet Zero Net Increase (ZNI) for stormwater runoff requirements.
Zero Net Increase for Stormwater Runoff
Urban redevelopment tends to replace natural pervious surfaces with impervious surfaces including rooftops, parking lots, and plazas. Increasing impervious surfaces increases both the peak flow and volume of stormwater runoff. Zero Net Increase (ZNI) for stormwater requires that post-development peak flows do not exceed pre-development peak flows for a wide range of rainfall events from the 2-year storm to the 100-year storm. ZNI requirements indicated that approximately 1,600 m3 of on-site detention storage was required.
In order to meet the ZNI requirement, on-site detention storage is typically used. Initially, conventional detention basins were considered for the MDC. However, the volume of on-site detention storage, the required footprint area, and public safety concerns indicated that an underground detention system (UDS) would be more appropriate for the location.
Underground Detention System
The City of Moncton evaluated a number of UDS technologies and products available. However, for this particular site, high groundwater elevations were a concern. Recognizing the former use of the site, there was a possibility that local soils and groundwater could be impacted by with contaminants. In recognition of this, it was determined that the UDS had to be a watertight system so that impacted groundwater could not migrate into the UDS and be conveyed to the storm outfall. This watertight requirement eliminated a number of UDS technologies and materials. In order to provide 1,600 m3 of on-site detention storage, the UDS was constructed with approximately 1.5 kilometers of 1,200mm diameter HDPE pipe in 18 rows complete with headers, inspection ports, and inlet/outlet connections.
UDS System Design
As with any watertight system in high groundwater conditions, buoyancy forces causing uplift of the UDS were a concern. The City worked closely with the engineering support provided by Soleno to ensure that adequate cover was provided over the UDS. Recognizing that the UDS was located beneath the MDC Plaza was another concern. A refrigerated ice surface and a soundstage were located directly above the UDS. Once again, the City worked closely with engineering support provided by Soleno to ensure that the UDS could withstand the dead load.
UDS Installation
The City recognizes that the bedding and compaction of flexible pipe is integral to ensure the structural integrity of the UDS system in order to prevent deflection of the flexible pipe. The City provided full-time construction inspection. Stantec provided full-time geotechnical inspection and testing. Soleno provided inspection of materials and installation as required throughout the UDS installation. Upon installation and bedding, each joint of the UDS system was inspected to ensure that there was no immediate deflection due to installation. Upon completion and backfilling, each joint of the UDS system was once again inspected to ensure there was no short-term deflection due to installation.
Closing
In recognition of the challenges to provide 1,600 m3 of onsite stormwater detention in an urbanized location where available footprint is limited and public safety is paramount; and in recognition of high groundwater conditions and the possibility of conveying contaminants off-site; a watertight UDS system constructed of HDPE pipe was the chosen to be the most appropriate technology to meet the site specific requirements.
Darryl Bonhower, P. Eng.
Project Engineer, City of Moncton